Modeling the process of network planning of a portfolio of projects with heterogeneous resources under fuzziness
A. A. Zatsarinnya, V. V. Korotkovb, M. G. Matveevb a Federal Research Center “Computer Science and Control” of the Russian Academy of Sciences, 44-2 Vavilov
Str., Moscow 119333, Russian Federation
b Voronezh State University, 1 Universitetskaya Pl., Voronezh 394018, Russian Federation
Abstract:
The paper discusses the problem of project portfolio scheduling subject to resource
constraints and fuzzy activity durations. Employees of various specializations are considered as the
only type of resource. Fuzzy W-algebra was used to avoid such difficulties and limitations of
traditional fuzzy arithmetics as the support size extension, the need of fuzzy
number comparison,
and some others. The proposed model provides a fuzzy estimation of project execution times and
optimal resource allocation. To solve the problem,
the genetic algorithm based on activity list representation was
implemented. The paper also provides a numerical example which
demonstrates advantages of applying the approach to organizations' workflow in the case of making
estimates for decision making under uncertainty.
Keywords:
project management, W-algebra, fuzzy arithmetic, combinatorial optimization, genetic algorithm.
Received: 28.03.2019
Citation:
A. A. Zatsarinny, V. V. Korotkov, M. G. Matveev, “Modeling the process of network planning of a portfolio of projects with heterogeneous resources under fuzziness”, Inform. Primen., 13:2 (2019), 92–99
Linking options:
https://www.mathnet.ru/eng/ia598 https://www.mathnet.ru/eng/ia/v13/i2/p92
|
Statistics & downloads: |
Abstract page: | 224 | Full-text PDF : | 77 | References: | 38 |
|